COVID 19

Council has implemented strict protocols to ensure we comply with directions issued by government in relation to managing the COVID 19 risk. These protocols apply to our staff, our customers and visitors to our premises, and councillors alike. Please be understanding that we will do our best to maintain services and help in what are unique and challenging circumstances.

For all your questions on COVID-19, please click here

Updated: December 2021

Over the past three years, works have been undertaken to Council’s ageing timber bridges to remove the imposition of load limits that would be required for some of these structures to ensure they did not fail before rectification works or total replacement could be carried out.

Council has been successful in obtaining some Federal Government and State Government Grant funding towards replacing existing structures and Council is continuing to seek further grant funding towards renewing the timber bridge infrastructure.

 

BRIDGE INFORMATION

Bridge No 67203

Unnamed Creek – Paddys Flat Road (North)

Works:  Temporary bridge in place. Council has engaged a contractor to design / construct a concrete replacement structure and it is programmed for construction during 2022.

Current:  Speed limit and restricted width clearance of 3 metres in place

 

Bridge No 67161 – Load Limit – 14 t GVM, maximum axle load of 6 t

Unnamed Creek – Paddys Flat Road South

Works:  Council has designed a replacement structure using large concrete box culverts and this project is being programmed for construction to commence early in 2022.

Current: Load limit and speed restriction signage to remain.

Detour:  Old Bruxner Road to access the Bruxner Highway.

 

Bridge No 67202 – Load Limit – 10 t GVM, maximum axle load of 5 t

Kangaroo Creek – Paddys Flat Road (North)

Works: Grant funding has been approved for the bridge replacement under the Australian Federal Government Bridges Renewal Program Round 4. Council has engaged a contractor to design / construct a concrete replacement structure and it is programmed for construction during 2022.

Current: Load limit and speed restriction signage in place. Pending completion of bridge replacement.

Detour:  Bruxner Highway to Clarence Way to Urbenville

To Commence: During 2022

 

Bridge No 73901

Deepwater River – Torrington Road

Works: Grant funding approved for bridge replacement (Australian Federal Government Bridges Renewal Program Round 4). The old timber bridge has been removed and foundation works completed for the new concrete structure. While weather and flooding delays had been encountered, new concrete girders were placed late February and works continue to complete the bridge.

Current: Bridgeworks temporary speed limits of 20km/h are in place and a narrow 3.0m wide temporary detour bridge is in place.

To Commence: Works are underway and planned to be completed by the middle of 2022.

 

Bridge No 62431

Washbrook Creek – Leeches Gully Road

Works:  Council has designed a replacement structure using large concrete box culverts and this project is being programmed for construction in the first half of 2022.

Current: Council has been successful in obtaining grant funding to replace the bridge. The road is now closed to through traffic and initial works have commenced to remove part of the existing timber bridge and as weather conditions permit, the remainder of the bridge will be replaced with new concrete structure.

Detour:  Old Ballandean Road

To Commence:  Design works are being undertaken and culvert materials have been sourced for the project.